Potentiële windturbine-installaties op basis van prototype

100.000

De toekomstige windturbines voorzien in de toekomst elk jaar woningen van stroom.

Op dit moment bekeken

De uitdaging

Het winnen van energie uit wind is een krachtig instrument om de doelstellingen van de energietransitie van onze samenleving te realiseren. Een windturbine met een capaciteit van 1,67 megawatt (MW) kan bij een capaciteitsfactor van 33% binnen 94 minuten genoeg energie genereren om een gemiddeld Amerikaans huis een maand lang van stroom te voorzien.

But before we can source energy from a field of wind turbines, it’s all about perfecting the prototype.

A wind energy company was ready to bring their latest wind turbine design to life. Needing an experienced engineering partner to design and construct the infrastructure required to build the prototype, the company selected Arcadis to lead the engineering, procurement and construction (EPC) of this latest project.

De oplossing

Windturbines zijn enorme constructies die wel 165 meter hoog kunnen worden, met bladen met een spanwijdte die groter is dan die van een rugbyveld. De voorbereiding voor de bouw van een windturbine is geen kleinigheid – een uitdaging waarvoor creativiteit, samenwerking en probleemoplossende vaardigheden nodig zijn. Ons team van experts ging als leidend EPC-bedrijf onmiddellijk aan het werk met het plannen en coördineren van de logistiek van het prototype-windturbineproject.

The foundation was a critical component. It was imperative to design proper roads, turbine pads and crane pads to account for the heavy equipment loads and massive crane operations. Cranes needed to lift equipment that weighed as much as 100 tons, which demanded strong geotechnical expertise and civil design to ensure that wind turbine components were delivered securely and that the cranes performing the lifts had a stable operational foundation based on solid understanding of the soil mechanics.

Working during the COVID-19 pandemic added new layers of difficulty to the complex prototype build. Since the wind turbine was a prototype, the team did not have replacements for any broken or misplaced materials. Plus, the pandemic exacerbated the shortage of materials and laborers, so plans were thoroughly scrutinized at every step to maximize available resources.

In addition to providing technical expertise on permitting, civil design, electrical design, civil construction and construction management, we had to be flexible, responsive and timely in order to deliver the project under uniquely challenging conditions.

De impact

Het prototype van de windturbine wordt nu gedurende een testperiode van twee jaar ingezet om gegevens te verzamelen en het ontwerp te analyseren, terwijl er stroom wordt opgewekt voor lokale gemeenschappen. De windturbine wordt toegevoegd aan het assortiment hoogwaardige windturbines van de organisatie zodra het onderzoek is afgerond. Het perfectioneren van deze ontwerpen helpt onze klant om zijn missie te volbrengen en onze wereld voor toekomstige generaties uit te rusten met betaalbare, betrouwbare en duurzame energie. 