You have not accepted cookies yet

This content is blocked. Please accept marketing cookies. You can do this here.

Simon Rawlinson

Head of Strategic Research and Insight

Building Infrastructure – Electricity Transmission

The GB electricity Transmission Owners hold the key to the UK’s energy transition but face huge challenges delivering their investment programmes. Mark Docherty and Simon Rawlinson of Arcadis summarise the current state of play.


Introduction – the opportunity of the UK’s grid upgrade.

Electricity towers and power lines stand tall against a stunning sunset backdrop, illustrating the harmony of energy and the environment.

Long before the Government committed to delivering a Net-Zero electricity network by 2030, The UK’s 3rd electricity revolution was well underway. Announcements made at the recent International Investment Summit including Iberdrola’s pledge to double UK capex through Scottish Power to £24 billion are the product of years of effort in the refinement of regulation, development of project proposals and raising of finance.

The GB Transmission Owners (TOs) plan to invest £20billion in twenty-six strategic projects under the regulator’s Accelerated Strategic Transmission Investment (ASTI) framework. The TOs will also continue to maintain and enhance the existing 8,600km grid, with a new price control period, RIIO-ET3, commencing in 2026. The period to 2040 will see investment of a further £58bn according to the National Energy System Operator’s (NESO) Beyond 2030 report, published in March 2024.

  • READ MORE

    Regulated network owners that have been focused on resilient and reliable network operation and efficient asset management are now leading some of the UK’s largest and most complex investment programmes. Their performance, alongside that of the regulator Ofgem, the planning inspectorate and the specialist electricity supply chain will be a critical success factor in ensuring that the UK has the grid in place to transmit power from many new large-scale offshore wind farms. Delay will not only mean that net zero targets are missed, but that consumers will pay curtailment costs to compensate generators for not being able to trade their output. Curtailment costs added £1 billion to bills in 2023.


    Despite the climate change imperative, grid programmes must be delivered within constraints including those associated with planning, value for money and industry capacity. The new Government has wasted no time in moving to approve grid investments through the Nationally Significant Infrastructure Planning process (NSIP) including a new Bramford to Twinstead 400kV transmission reinforcement. Work is in full swing to build the delivery enterprises needed to deliver a 6-times increase in workload.


    The TO’s procurement strategy highlights a special dimension to the UK’s grid upgrade, an extreme level of international competition for supply chain capacity. Bloomberg NEF calculates that 80 million km of cable will be needed for transmission and distribution grids by 2050. The production of high voltage cable and switchgear continues to be a highly-skilled process that is difficult to scale-up. Similarly, demand for labour is set to be a problem, particularly for skills associated with high voltage cable and equipment. With global demand outstripping capacity, TOs and Ofgem face difficult trade-offs when securing production slots to provide assurance around efficiency and value for money.


    In summary, investment in the grid must meet the triple challenge presented by ageing networks, energy transition and soaring electricity demand for heating homes and charging cars. TOs will need innovation in technology, process, and organisation to ensure that their enabling infrastructure is in place, on programme. The NESO’s latest report, Clean Power 2030, published in November 2024, confirms that the objective is deliverable, but that it can only be achieved by doing things differently. TOs will need innovation in technology, process, and organisation to ensure that their enabling infrastructure is in place, on programme.

The 2030 grid challenge.

Detailed close-up of a large electrical substation, highlighting transformers and power distribution elements in a complex layout.

The transmission grid has a crucial role in enabling the net-zero transition. Offshore wind farm developers depend on timely completion of new HVDC converter stations to export their output. Additional supergrid expansion and reinforcement is required to address emerging capacity constraints and new grid services from storage and stability providers will need transmission connections.

Issues that contribute to the complexity of the challenge include:

  • Complexity of a renewables-based network.

    The shift from electricity generation from gas to offshore wind has implications that go well beyond geography. Grids based on renewables are typically more complex, have a larger number of smaller, transmission and distribution connections and are less stable due to production variability. Modern electricity networks have a greater reliance on ancillary services to maintain stability and resilience, such as the Greener Grid Park model, which combines multiple, standardised, grid connections for a variety energy sources, including battery storage, as well as large-scale inertia devices that maintain grid stability.


    Geography also adds complexity. With new capacity being developed to the North and West of Scotland as well as in the North Sea, many schemes will be delivered in remote locations, creating additional logistical challenges including access provision, materials delivery, and accommodation for a large, imported workforce. The sheer scale of development also presents problems for the developers and stakeholders. The 400kV network extensions under development, often replacing existing 132kV infrastructure, typically require larger and more visible towers and sub-stations. Similarly the converter stations for high capacity HVDC links are enormous - typically 200m long by 40m wide. All options, overhead line (OHL), underground cable and HVDC links have visual and environmental impacts that can be difficult to mitigate.

  • Diverse network solutions.

    Components of the grid have distinct functions which in turn can affect the regulatory model and the parties involved in development. The NESO’s Holistic Network Design document (2022) set out a range of transmission network developments to facilitate the connection of the 23 GW of new offshore wind projects. The evolving transmission system will comprise significant enhancements to the legacy onshore transmission networks as well as the expansion of legacy networks with offshore HVDC links including those between Scotland and England. Other additions will include dedicated offshore transmission wind farm connections, integrated offshore transmission solutions that connect multiple offshore generators and HVDC interconnectors linking neighbouring European transmission grids that enable the efficient transfer of energy surpluses and deficits. As a result, a range of parties are involved in the delivery of different components of the future transmission system with the potential to disaggregate demand for cable, equipment, and contractors.

  • Simultaneous demand.

    With the world racing towards a single net zero transition date, every grid requires transformation. Although the transformation has been anticipated for at least a decade, in practice, actual demand only crystalised from 2019 onwards. Manufacturers (OEMs) serve other markets including distribution networks and must allocate investment across all voltage levels. Without a visible pipeline, equipment, and cable manufacturers (OEMs) chose to invest incrementally into new HV capacity and were caught out by a 3 to 4 times increase in demand. Lead times for equipment such as transmission voltage transformers are up from 30 to 60 weeks to 120 to 210 weeks according to Wood McKenzie.


    High levels of demand affects the wider delivery model. OEMs are focusing their operations solely on the manufacture and installation of their equipment. Turnkey contracts for converter stations and other major works are becoming harder to secure with Civils Contractors increasingly being engaged directly to undertake the building and Balance of Plant (BOP) works.


    Supply chain constraints will also affect the pace of installation. Ground investigations require a significant increase in the availability of mobile drilling rigs and marine cable laying will be dependent on access to scarce specialist vessels. A rapid explosion in demand could result in TOs competing to secure capacity. Consolidated programmes and regulatory models that permit early procurement to secure capacity are an important aspect of comparative advantage in energy markets. Ofgem’s ASTI model facilitates this by allocating pre-construction and early construction funding.

  • Concentrated supply chains.

    The cable and equipment markets are highly concentrated and have extremely high barriers to entry meaning that new sources of competition is rare. Three manufacturers each separately dominate the UK and European Cable and Transformer markets with a share of 75% of capacity. It is forecast that by 2025, there will be a 1,000km pa shortfall in HVDC cable manufacture. TOs and their regulators have had to adapt their procurement strategy in response – for example by funding early payments to secure manufacturing slots. As an illustration of an extreme response to the constrained supply chain, X Links, the UK-Morocco power project, proposes to develop its own manufacturing facility in Scotland to deliver 4,000 km of HVDC cable to the project before serving the wider interconnect market.

  • Stakeholder buy-in to proposals through the planning process is of course a major blocker.

    Planning reform is a key element of the changes identified by in the 2023 Winser Review to reduce project durations to an average of 7 years. The review highlights multiple issues in the planning system including a lack of guidance for trade-offs and the need for rules on public benefit and compensation. The pace of reform to the planning system continues to accelerate with the forthcoming Planning and Infrastructure Bill and updates to the Energy National Policy Statements (NPS). The EU has already adopted a ‘presumption of overriding public interest’ to simplify the approvals processes for grids and in the UK, the grid is defined as Critical National Infrastructure. Further measures are likely to be needed to meet connection deadlines.

  • Specialist skills.

    Construction’s transmission sector has a well-known skills shortage that could be difficult to resolve. The critical skills requirements, design engineering, field engineering, tower erection, OHL stringing and electromechanical engineering require relatively few specialists compared to the wider, general workforce but are all under high demand and have a long-lead in period for training and skills acquisition. Arcadis undertook a labour market study in 2022 with Contractor Murphy which highlighted that an industry-wide response, including the provision of training opportunities and mid-career development, would be needed to ensure growth in the workforce in line with demand. A particular problem is the supervisory constraint on on-site training, particularly in live environments. One option available to delivery organisations will be to access an overseas labour force. Currently the UK’s points-based system supports this based on qualifications and earnings thresholds. TOs in Europe are already exploiting open borders in the EU to access specialist labour, and UK employers will need a compelling offer to attract the best people whilst building a domestic workforce.

Box feature – critical trade-offs in grid design.

An expansive electrical substation filled with multiple wires and poles, illustrating the intricate network of power transmission.

Transmission grids can be visually intrusive and inevitably generate high levels of opposition from local populations affected by the new infrastructure. In general, the GB TOs confirmed that HVAC OHL would be their preferred network expansion and reinforcement approach in 2023, which has helped to provide some clarity to the planning process. In the context of the GB transmission network, HVAC OHL networks provide an optimum combination of whole life cost, efficiency, reliability, and maintainability. Buried cables are also used in locations that are visually sensitive although the installation process can be disruptive. A double-circuit transmission cable swathe can be over sixty metres in width. Although there will be some access structures and potentially some legacy limitations on planting, underground installations are usually difficult to spot once vegetation is reestablished.

  • READ MORE

    The scale and impact of modern transmission networks and the strong economic case for OHL circuits means that affected stakeholders may find it harder to successfully object to new infrastructure. The planning process is still time consuming and risky – particularly given that ‘alternative proposals’ including underground options must be examined in detail. The rapid development of an acceptable compensation scheme is now a critical enabler for the 2030 net zero deadline.


    Other options include OHL reconductoring using higher capacity/temperature conductors on existing towers and voltage upgrades. Such reconductoring can provide some additional capacity, but in the context of the scale of the energy transition, may only represent a short-term solution. Affected stakeholders have also argued for the use of HVDC undersea cables, but these are uneconomic over shorter distances and can be difficult to integrate into an existing grid without creating additional capacity constraints.

Box feature – experience from Europe.

A vast electrical substation with an array of wires and poles, representing the essential components of electrical infrastructure.

Arcadis has a prominent role in the design and delivery of transmission grids in Europe including delivery via EPCM of new grid infrastructure for TO, TenneT in Germany and the Netherlands. Our experience highlights the shared challenges faced by all TOs as well as some of the comparative advantages that some countries have because of ownership or regulation.

Commonalities between TOs include a lack of common standards between the grids within a country as well as the universal challenge of securing access to equipment and cable OEMs. Public procurement regulations are another common factor. TenneT is owned by the Dutch State and is the sole Transmission and System Operator (TSO) for the Netherlands. However, the legacy grid was developed on a regional basis by multiple network operators, and as a result is subject to similar levels of variation in standards seen across Germany. As a State-owned entity, TenneT is publicly accountable but is not subject to the same level of competition regulation seen in the UK and Germany. This creates some freedoms, such as the ability to set technical standards and to pre-purchase cable and equipment in advance of production. For example, over 5,000 km of HVAC cable has been secured at a cost of €4.8 billion. As a single entity, TenneT in the Netherlands is also able to standardise new requirements – particularly with respect to the technical and civils design for new connections to wind parks in the North Sea.

  • READ MORE

    By contrast, TenneT in Germany is one of four TSOs operating in Germany and it’s programme is subject to more extensive economic regulation. The regulatory model is being adapted to facilitate bigger programmes delivered by strategic partnerships, benefitting from private sector innovation. Competition between TSOs, and the approvals process limits opportunities for early contractor engagement, bulk procurement and to a lesser extent, standardisation.


    Although both the Netherlands and Germany have applied an EU-sponsored critical infrastructure planning presumption, which simplifies environmental assessment requirements, permitting processes inevitably remain contentious.

Procurement – finding the best fit option.

 A large tower equipped with wind turbines stands beside a boat on calm waters, showcasing renewable energy in action.

For transmission, procurement strategy must address three key objectives:

  • Access to critical supply chain capacity
  • Development of a commercial model that assures timely delivery and achieves an optimum risk allocation.
  • Achievement and demonstration of efficiency and value for money to protect customer interests and to assure returns on investment.

Procurement doesn’t take place in a vacuum and the GB TOs are competing with public and private sector utilities across Europe for the same equipment and cable supply chain. Although all work is let using public procurement processes, some utilities have a head start, such as TenneT in the Netherlands (See Box Feature)

  • READ MORE

    Reliable long-term access to OEM capacity can be secured through advanced payment for manufacturing and project slots. TOs that have the flexibility to procure at scale have a significant source of comparative advantage but presently, the GB’s TOs take some commercial risk when undertaking advanced purchasing in advance of final programme approval.


    The optimum commercial model brings together the Civils Works programmes alongside the OEMs. All GB TOs are putting in place frameworks to secure access to capacity, but the contract model varies, ranging from a single-point EPC arrangement to a more disaggregated ‘mega-package’ where the client’s management team undertakes the package coordination. The contract model in turn has implications for the management capability of the TO and their capacity to coordinate and manage multiple contractors on multiple, parallel programmes.


    Demonstrating efficiency and value for money is a core function of the UK’s regulatory model. Different public procurement regulations apply to Scotland and England and Wales which determine options for competition. Regulation has a significant impact on procurement strategy, and the regulatory model used for the grid upgrade has been modified to support TOs in their development of programmes, to contract early for capacity and to increase speed of turn-around. Ofgem is typically engaged earlier, but final approval under the Accelerated Strategic Transmission Investment (ASTI) framework ideally requires key milestones to have been achieved, such as DCOs being granted, main works contractors being appointed and a demonstrable basis for efficient project costs.


    Demonstrating efficiency is much harder in a hot market and TOs are exposed to a long-term revenue risk if they cannot demonstrate value for money. Ofgem and the TOs both recognise this problem. A suite of tools including should-cost benchmarking, best practice open-book estimating, competition where available and effective governance and controls will support the demonstration of efficiency. Typically, OEMs responsible for cable and equipment bid on a closed-book basis, so much of the focus on value sits with the Civils packages and Balance of Plant works (BOP) where bottom-up estimates are subject to detailed assessment.


    Achieving cost certainty is the final part of the jigsaw but given the scale of the programmes and the level of competition for resources, the TOs have limited leverage on their supply chain. To some extent, TOs can secure allowances for additional costs through price adjustment mechanisms for market driven changes such as increases in commodity and labour costs. Given that the transmission sector needs to remain investable to attract investment, TOs and the regulator will need to work very closely to ensure that projects remain deliverable and viable.

The transmission sector is a key link in the chain that will deliver a net zero future. The UK’s current investment push aims to decarbonise the existing grid, but that is only the first step in the challenge. Transmission grids will continue to expand to accommodate the increases in power generation capacity required for heating, EV charging and industrial processes. electricity distribution grids will also require extensive reinforcement over time to cope with new loads and new connections. In line with the 2050 Net Zero target, this process will happen everywhere – the resource shortages seen today are the new normal, not a one-off blip. Lessons learned through this first phase of grid expansion will continue to be essential, long into the future.

Originally published in Building

Connect with {name} for more information & questions

Arcadis will use your name and email address only to respond to your question. More information can be found in our Privacy policy