The challenge
Concerned by the poor crash history, the NSW and Federal governments funded an upgrade of the 2.1km stretch of road to make the highway safer.
Concerned by the poor crash history, the NSW and Federal governments funded an upgrade of the 2.1km stretch of road to make the highway safer.
Arcadis worked closely with Transport for NSW to develop several bridge options before the final design that best met the project goals.
The improved safety and efficiency will bring benefits to locals, freight operators and many tourists who rely on the New England highway.
of highway upgrade with a poor crash history
long balanced cantilever bridge in challenging terrain
longest balanced cantilever bridge in NSW
The stretch of the New England Highway 35km south of Tenterfield at Bolivia Hill had a poor crash history due to an unforgiving 2.1km of steep, winding road with narrow lanes and minimal shoulders, a rock face on one side and a steep valley below on the other. Concerned by the poor crash history, the NSW and Federal governments funded a much-needed upgrade of the highway, with the objective of making the highway safer and more efficient for road users.
Arcadis was engaged by Transport for NSW to undertake the concept design, detailed design and a Review of Environmental Factors for the project. Particularly challenging for Arcadis was the constraints to construction access and traffic management presented by the difficult terrain, together with the presence of the endangered Bolivia Wattle across the preferred alignment.
The Bolivia Hill Upgrade involved realigning the highway to remove the most dangerous curves, requiring construction of a 320m-long bridge across a large valley and retaining walls on the bridge approaches. During the Concept Design phase, Arcadis worked closely with Transport for NSW to develop several bridge options before the preferred option was selected. Arcadis designed a three-span cast in-situ concrete box girder bridge, with the 150m-long central span bridging the area of Bolivia Wattle within the valley below. The bridge was constructed using the balanced-cantilever method, which involves casting the bridge deck sequentially in short segments on either side of the two piers, maintaining the two cantilevers in balance, continues until the deck cantilevers extending from the piers reach each other and is completed with closure segments in the centre span. This method allowed a longer main span to be achieved which avoided impacts on the Bolivia Wattle and minimised the extent of temporary access tracks required in the steep terrain, reducing the cost and environmental impact of the project.
The bridge is founded with pad footings bearing on the granite bedrock and anchored down with ground anchors. The two piers consisting of twin reinforced concrete blades cast integrally into the superstructure, which varies in depth from 8m at the piers to 3.5m at mid-span.
Safety in construction and operation was paramount for the design. Our design removed working at heights requirements for bearing replacement by adopting integral pier connections, incorporated the existing highway into a safe parking area for maintenance workers and removed longitudinal drainage pipes from the underside of the superstructure to avoid the need for routine inspections from the bridge design. These key design details will continue to deliver safety benefits for Transport for NSW workers well into the future.
Arcadis is proud to have delivered the Bolivia Hill Upgrade, a complex and challenging project that is expected to bring numerous safety and efficiency benefits to locals, freight operators and many tourists who rely on the New England highway as a gateway to multiple NSW holiday destinations. We delivered a major piece of infrastructure for regional NSW that will improve road safety for people in the communities of Tenterfield and New England regularly travelling through Bolivia Hill and avoided impacts on an endangered piece of flora that is only found at Bolivia Hill.